How to install aluminum alloy cable?

  • news2021-07-05
  • news

aluminum alloy cable

 

 

 

Aluminum alloy cable installation process

1. Confirm the route

        According to the demand of photovoltaic project, the aluminum alloy cable line needs to ensure the safe operation of the project, facilitate maintenance, and fully consider the ground environment, soil data and various underground road facilities, so as to reduce the use of cables, save expenses, and reduce the loss and reactive power caused by cables. The preliminary requirements are as follows:

1) Optimize the use of aluminum solar cables, choose the shortest distance path, reduce loss and save costs.
2) Plan the cable path as a whole to reduce repeated excavation of cable trenches;
3) Minimize the number of crossing pipelines, railways and other power cables, and reduce the number of crossing walls and floors;
4) Reduce the damage to the cable from environmental factors, and prevent the cable from being affected by external mechanical forces, chemical corrosion, vibration, and geothermal;
5) Drainage ditch, gas pipe, main water supply pipe, weak point line, etc. are provided on one side of the road, and the power cable should be laid on the other side of the road.

 

2. Choose the appropriate terminal

        There are some problems in the production of AC terminals on the project site, mainly:
1) The connecting terminals do not match
        The more prominent problem in the domestic promotion and application of aluminum cables is that matching connectors are difficult to purchase. Therefore, some sites use copper-aluminum transition terminals or other alloy connectors that do not match the performance of aluminum alloy cables. Such usage cannot guarantee the safe use of cables and will leave hidden dangers.
2) Inconsistent terminal size
        At present, most power terminals, including complete sets of electrical design, adopt copper cable specifications and size standards. Aluminum cables or aluminum alloy cables are different from copper cables due to their current carrying capacity. During use, the cross-sectional area is increased to meet the current-carrying requirements, which causes the cable to be mismatched with the original electrical installation hole size. At present, the common method is to transfer copper bars, or to wear down or cut off part of the conductor to reduce the cross-sectional area. Both of these methods will bring greater safety hazards.
3) Irregular crimping during installation
        In the process of communicating with EPC manufacturers, I often hear the saying “The installation and construction of aluminum cables or aluminum alloy cables must be performed by experienced electricians”, because a place that is not noticed during the construction process may be As a result, the power station cannot operate efficiently and safely. At the same time, for the use of “aluminum cables and aluminum alloy cables must use professional tools, can not operate according to the production process of copper cables”, the follow-up content will describe the production process of aluminum alloy cables in detail.

 

        Through the description of hidden dangers, choosing the right connecting terminal for aluminum or aluminum alloy cable is the first step to exert the cable performance. At present, there are three types of terminals on the market suitable for aluminum alloy cables, including copper terminals, copper-aluminum transition terminals and aluminum alloy copper transition terminals.

a. Copper terminal: It is the most common terminal, but due to the electrochemical corrosion between copper and aluminum and the inconsistent physical and mechanical properties, there will be certain hidden dangers in the quality of photovoltaic projects.

b. Copper-aluminum transition terminal: It is a widely used terminal for aluminum cables and aluminum alloy cables. The terminal is composed of two parts, one end is used to connect the aluminum wire and aluminum alloy cable, and the other is In order to connect complete sets of electrical or other power terminals, common copper-aluminum transition terminals are divided into DTL-1, DTL-2 and pin-type copper-aluminum tubes according to their shapes.

 

copper-aluminum transition terminals

 

        At the same time, some installation manufacturers take into account the different electrochemical properties of copper, aluminum and aluminum alloys, and will apply the conductive paste to the aluminum tube. This approach can effectively reduce the corrosion of the aluminum tube.

 

3. Installation and crimping of aluminum alloy cables and connecting terminals

        The connection between the cable middle and the terminal directly affects the reliability of the entire system. In some projects, professional tools are not used for the crimping of aluminum alloy cables, which leads to hidden safety hazards or accidents in the project.

 

1) List of installation and crimping tools for aluminum alloy cables

Machine name Unit Quantity Usefulness
1 Cable insulation stripping tool piece 1 Strip the cable insulation
2 Electrician’s Knife piece 1 Strip the cable insulation
3 Steel brush piece 1 Clean up debris on the conductor surface
4 Tape measure piece 1 Measure the length of the insulation stripped
5 Vise piece 1 Tool
6 Needle nose pliers piece 1 Tool
7 Cable terminal piece Several Connection
8 Crimping pliers and crimping dies piece 1 Crimping of cable terminals
9 Gloves pair 1 Protection
10 Cleaning cloth 1 1 Clean

 

 

2) Installation steps of aluminum alloy cable

Installation steps of aluminum alloy cable

 

Installation of aluminum solar cable

 

 

4. Acceptance and maintenance of aluminum alloy project

        The cable test should not only inspect and discover the defects of the cable line to ensure the healthy and safe operation of the equipment, but also accumulate data and experience through the test to provide science for the formulation of anti-accident measures, equipment technical transformation and improved operation management. Therefore, this work must be done well.

 

summary

        In the process of grid parity for photovoltaic systems, under the premise of ensuring the quality of power stations, the application of suitable new materials and new technologies is a general trend. Therefore, the use of new materials not only requires manufacturers to provide products with reliable quality, but also requires installation and maintenance in strict accordance with the requirements to ensure the full life cycle of photovoltaic projects.

Dongguan Slocable Photovoltaic Technology Co.,LTD.

Add:Guangda Manufacturing Hongmei Science and Technology Park, No. 9-2, Hongmei Section, Wangsha Road, Hongmei Town, Dongguan, Guangdong, China

TEL:0769-22010201

E-mail:pv@slocable.com.cn

facebook pinterest youtube linkedin Twitter ins
CE RoHS ISO 9001 TUV
© Copyright © 2022 Dongguan Slocable Photovoltaic Technology Co.,LTD.Featured Products - Sitemap 粤ICP备12057175号-1
solar cable assembly, cable assembly for solar panels, pv cable assembly, mc4 extension cable assembly, solar cable assembly mc4, mc4 solar branch cable assembly,
Technical Support:Soww.com